土耳其伊斯坦布尔新机场的建设已完成80%,预计于10月29日开始投入使用,预计项目费用为123亿美元。机场第一阶段建设完成后,将建成三个独立并行的跑道、滑行道、航站楼、空中交通管制塔和通信与天气系统可供使用。在运营初期,机场预计每年可接纳乘客9000万人次。机场所有建设阶段有望于2028年完工,届时机场每年的运客量预计将达到2亿人次。
报道原文如下:
Construction of Istanbul New Airport in Turkey is 80% complete, with the initial phase slated to open on October 29. The estimated cost of the project is USD12.3bn. once complete, the first phase of the airport will have three independent and parallel runways, taxiways, terminal building, air traffic control tower, communication and weather systems. In the initial phase, the airport is expected to accommodate 90mn passengers annually. IGA is the engineering, procurement and construction contractor and operator for the project. The 3.75km long and 60m wide first runway at the airport is complete, according to IGA CEO Yusuf Akçayoglu (TradeArabia). When all phases of the airport are complete in 2028, the annual passenger capacity of the airport will reach 200mn, according to GET.